Commercial HVAC Installation
Construction Date: February 2015
Location: McDonald’s Bridgewater, NJ
Commercial HVAC Installation Scope
- Shut down unit and lock out electrical power supply.
- Recover and dispose of refrigerant charge per the EPA Guidelines.
- Includes crane and rigging service.
- Remove and properly dispose of existing units.
- Install two (2) 5 Ton new packaged rooftop units onto existing curb adapters.
- Install new refrigerant lines and connect to existing supply and return ducts.
- Connect electrical to existing unit disconnect.
- Install new electrical and conduit from junction box to unit disconnect and terminal board where new unit footprint requires this.
- Reconnect existing electrical and control wiring.
- Install new condensate drain lines as needed.
- Provide Lennox factory start-up and First Year Warranty.
- Provide a Certified Test and Balance on each new unit to confirm supply air Cubic Feet per Minute (CFM).
Project Goal: The goal was to successfully install the equipment and furnish materials, supplies, labor, and hardware to remove and install two (2) 5 Ton Lennox Rooftop Air Conditioning units.